Masons on eastern face pick up speed

Today an additional mason was added to the project, brining the total up to four. With approximately 15 feet of brick already covering the eastern wall facing the bookstore, this additional mason will increase the overall production. This rapid pace … Continue reading

Posted in Exterior Construction | Tagged , , | Leave a comment

Fabrication of precast exterior pieces almost done, shipping underway

At the concrete precast plant in Tecate on Tuesday August 27, almost all of the Annenberg exterior precast panels are completed. The final fabrication continues at full speed. The yard is full of panels ready to ship (see photos). The … Continue reading

Posted in Exterior Construction | Tagged , , , | Leave a comment