More precast ready for delivery

More pieces of precast concrete are ready for delivery to the construction site. This batch includes several pieces that have the Wallis Annenberg nameplate. Unlike some of the other buildings on campus, the engraved names were done during the precast process rather than needing to add scaffolding later and bring in an engraver to do the work on site when the precast is installed.

UPDATE (10/17/2013): nine to fourteen trucks (two or three a day) of precast are poised to be delivered to the site on Thursday October 17, with erection starting on the West Elevation on Friday.