Monthly Archives: January 2014

Exterior masonry wrapping up

The exterior brickwork is going up rapidly thanks to several dozen masonry workers adding brick to every exterior face of the building. Scaffolding around completed sections should start being removed next week, leaving sections of the building’s exterior looking very … Continue reading

Posted in Exterior Construction | Tagged , | 2 Comments

Then and now – Basement auditorium

Posted in Interior Construction | Tagged , , | Leave a comment

LADWP water connection established

Late last night (and this morning) crews completed the building’s water connections to the LADWP lines. The work went without a hitch and passed city inspections ahead of schedule. This paves the way for electricity to be turned on in the … Continue reading

Posted in Exterior Construction | Tagged , , | Leave a comment

Glass installed on second floor offices

In addition to the large exterior windows, many interior rooms have glass walls. This helps provide a more open feel to the building. The most recent area to get glass walls installed are these offices on the second floor overlook … Continue reading

Posted in Interior Construction | Tagged , | Leave a comment

Collaboration room walls going up

Perhaps one of the most exciting aspects of the new building are the extensive collaboration areas. This one on the third floor now has walls in place and is awaiting further development. Interior work on rooms such as this will … Continue reading

Posted in Interior Construction | Tagged , | Leave a comment

Newsroom raised flooring installed

Although students and staff were off for the holiday season, construction crews were hard at work. Among the myriad of areas that underwent change over the break, one of the most dramatic was the completion of wiring and installation of … Continue reading

Posted in Interior Construction | Tagged , , , | Leave a comment

Welcome to 2014!

Happy New Year from everyone at the Annenberg school! In just a few months until the construction of the building is complete!

Posted in Exterior Construction | Leave a comment