Monthly Archives: June 2013

“Summer Daze” faculty and staff tours

As part of the “Summer Daze” program, faculty and staff got tours of the new building.

Posted in Tour | Tagged , , | Leave a comment

Pouring concrete on the fourth floor (roof)

Pouring concrete on the fourth floor (the roof). Starting at 8:00 AM the pour took all day with some of the finishers working until after 6 PM. Like the other floor pours, once a pour is started the concrete is … Continue reading

Posted in Exterior Construction | Tagged , | 1 Comment

Prepping for roof concrete pour

The final preparations for the large concrete pour on the roof. With inspections completed, several hundred cubic yards of concrete are scheduled to be pumped to the roof tomorrow (June 21) where crews will work the concrete into the necessary … Continue reading

Posted in Exterior Construction | Tagged , | Leave a comment

Media center’s large windows framed

The north side of the building (facing the PED building) will have large windows that will provide a great backdrop to the new media center which will house a converged newsroom for Annenberg TV News, Annenberg Radio News, Neon Tommy … Continue reading

Posted in Exterior Construction | Tagged , , | Leave a comment

Future patio area

The south side of the building will feature classrooms with wide doors that open out onto a patio area (where the pile of gravel is now).

Posted in Exterior Construction | Tagged | 3 Comments

Second floor drywall going in

Now that the first floor has had shotcrete applied, crews can finish up the second floor’s drywall.

Posted in Exterior Construction | Tagged | Leave a comment